FLS Director immediately reports to the FCS and conducts a rapid assessment of existing conditions.
| ACTION |
| Secure area if possible. |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| Lock Doors, Post guards, Place physical barriers or tape off area to prevent access. |
| WHY |
| Isolate individual to prevent injury to others in the event of an explosion. |
| ACTION |
| Notify EAP Brigade to report to FCS. |
| WHO |
| FLS Director |
| HOW |
| Hand held radio, cell phone, or telephone. |
| WHY |
| Conduct an initial assessment of the Emergency based on all available information. |
| ACTION |
| Notify Authorities and Emergency Responders |
| WHO |
| FLS Director |
| HOW |
|
Call 911. Minimize use of radios and cell phones in area. Call 911 from hardwire phones if possible. |
| WHY |
Provide as much information as you can, such as:
|
| ACTION |
| Notify 660 FIFTH AVENUE Building Management Office at 646-948-7771. |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| Hand held radio, cell phone or telephone. |
| WHY |
| Provide information as described above. |
| ACTION |
| Determine EAP Response. |
| WHO |
|
FLS Director EAP Brigade |
| HOW |
| EAP Brigade "Huddle" at FCS or alternate internal meeting point. |
| WHY |
|
Provide protection and warning to the greatest number of Persons possible. * If individual is isolated and contained consider Shelter-in-Place. Evacuation or In-Building relocation may create large groups of people thus providing a target for the bomber. |
| ACTION |
| Implement EAP Response. |
| WHO |
| FLS Director |
| HOW |
| Inform Building Staff Members which EAP Response is being implemented and instruct them to report to their assigned area to carry out their duties. |
| WHY |
| Ensure the safety of the greatest number of Persons possible. |
| ACTION |
| Make a Building-wide Announcement including Stairway Speakers (4W’s). |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| PA System located at the FCS. |
| WHY |
Provide Occupants all available information including:
|
| ACTION |
| Maintain two-way communication with EAP Staff. |
| WHO |
|
FLS Director EAP Brigade |
| HOW |
| Portable Radios, Warden Phones |
| WHY |
| To monitor conditions and report on progress of operation. |
| ACTION |
| Establish liaison with Emergency Responders. |
| WHO |
|
FLS Director EAP Brigade |
| HOW |
| Meet arriving First Responders at Building Lobby. |
| WHY |
|
| ACTION |
| If explosion occurs: Implement Explosion-Bomb procedures.
NEVER APPROACH OR ATTEMPT TO RENDER AID TO BOMBER AFTER EXPLOSION. |
| WHO |
|
FLS Director EAP Brigade |
| HOW |
| Follow directions under "Explosion Bomb" incident information using the link below. |
| WHY |
| Provide appropriate Response should explosion occur. |
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| ACTION |
| Determine EAP Response. |
| WHO |
|
FLS Director EAP Brigade |
| HOW |
| EAP Brigade "Huddle" at FCS: Ascertain as much as possible and assess available Responses. |
| WHY |
| Provide protection and warning to the greatest number of Persons possible. *If individual is isolated and contained consider Shelter-in-Place. Evacuation or In-Building Relocation may create large groups of people thus providing a target for the bomber. |
| ACTION |
| Maintain two-way communication with EAP Staff. |
| WHO |
| FLS Director EAP Brigade |
| HOW |
| Portable Radios, Warden Phones |
| WHY |
| To monitor conditions and report on progress of operation. |
| ACTION |
| Establish liaison with Emergency Responders. |
| WHO |
| FLS Director EAP Brigade |
| HOW |
| Meet arriving First Responders at Building Lobby. |
| WHY |
|
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| ACTION |
| If the individual is unaware that he/she has been discovered attempt to discreetly alert others and clear the area. |
| WHO |
| Any EAP Staff |
| HOW |
| Word of Mouth, Telephone, E-Mail. |
| WHY |
| Upon discovery, bombers may detonate the explosive device rather than risk capture. |
| ACTION |
| If the individual is aware of being discovered clear the area immediately and alert any Persons nearby. |
| WHO |
| Any EAP Staff |
| HOW |
| PA System, Telephone, E-Mail, Bullhorn |
| WHY |
| Upon discovery, bombers may detonate the explosive device rather than risk capture. |

| ACTION |
| Secure area if possible. |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| Lock Doors, Post guards, Place physical barriers or tape off area to prevent access. |
| WHY |
| Isolate individual to prevent injury to others in the event of an explosion. |
| ACTION |
| Notify 660 FIFTH AVENUE Building Management Office at 646-948-7771. |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| Hand held radio, cell phone or telephone. |
| WHY |
| Provide information as described above. |
| ACTION |
| Make a Building-wide Announcement, including Stairway Speakers (4W’s). |
| WHO |
|
FLS Director Lobby Security |
| HOW |
| PA System located at the FCS. |
| WHY |
Provide Occupants all available information including:
|
| ACTION |
| Access to and Egress from Building. |
| WHO |
|
Lobby Security Critical Operations Staff |
| HOW |
| Position EAP Staff at all points of Access/Egress. |
| WHY |
|
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| ACTION |
| Assess/Monitor all Building Components. |
| WHO |
|
Critical Operations Staff Building Engineers |
| HOW |
| Members of the EAP Staff are assigned to assess a pre-determined Building Component according to the Building’s EAP. |
| WHY |
| Ensure all Building Components are assessed to allow for implementation of the EAP. |
| ACTION |
| Access to and Egress from Building. |
| WHO |
|
Lobby Security Critical Operations Staff |
| HOW |
| Position EAP Staff at all points of Access/Egress. |
| WHY |
|
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| ACTION |
| Notify Brookfield Properties Corporate Office at 212-417-7000. |
| WHO |
|
Property Manager Assistant Property Manager Administrative Assistant |
| HOW |
| Telephone, E-mail, Initiate Workspeed. |
| WHY |
| Provide information as described above. |
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |

| ACTION |
| Assess/Monitor all Building Components. |
| WHO |
| Critical Operations
Staff Building Engineers |
| HOW |
| Members of the EAP Staff are assigned to assess a pre-determined Building Component according to the Building’s EAP. |
| WHY |
| Ensure all Building Components are assessed to allow for implementation of the EAP. |
| In addition to the Actions shown above, ALL STAFF MEMBERS must be familiar with, and prepared to perform, the following Actions designated for ANY EAP STAFF Member for this incident. |