FLS Director immediately conducts a rapid assessment of existing conditions.
| ACTION |
| Notify EAP Brigade to report to FCC. |
| WHO |
| FLS Director |
| HOW |
| Notify EAP Brigade to report to FCC. |
| WHY |
| Conduct an initial assessment of the Emergency based on all available information. |
| ACTION |
| Notify the JSOC at 212-417-7116 & Property Management Office at 212-528-2179. |
| WHO |
| FLS Director
EAP Brigade |
| HOW |
| Hand held radio, cell phone, or telephone. |
| WHY |
| Provide information as described above. |
| ACTION |
| Ensure Emergency Backup Generator has been activated and is functioning properly. |
| WHO |
| FLS Director
Building Engineers |
| HOW |
| Conduct onsite inspection of Systems. |
| WHY |
| Provides Backup Power to Building Life Safety Systems. |
| ACTION |
| Ensure Life-Safety Systems are operating.
Conduct a visual inspection at FCC and BMS. |
| WHO |
| FLS Director
Building Engineers |
| HOW |
| Conduct a visual inspection at FCC. |
| WHY |
| Failure of any Life-Safety Systems would require a possible Building Evacuation. |
| ACTION |
| Notify Authorities and Emergency Responders. |
| WHO |
| FLS Director |
| HOW |
| Call 911 |
| WHY |
State the following information:
|
| ACTION |
| A Power Outage does not automatically require an Evacuation of the Building; implementation of the Emergency Action Plan should be considered.
Determine EAP Response. |
| WHO |
| FLS Director
EAP Brigade |
| HOW |
| EAP Brigade “Huddle” at FCC: Ascertain as much information as possible and assess available Response. |
| WHY |
| Provide protection and warning to the greatest number of Persons possible. |
| ACTION |
| Implement EAP Response (if required) |
| WHO |
| FLS Director |
| HOW |
| Inform Building Staff Members which EAP Response is being implemented and instruct them to report to their assigned area to carry out their duties. |
| WHY |
| Ensure the safety of the greatest number of Persons possible. |
| ACTION |
| Make a Building-wide Announcement including Stairway Speakers (4W’s).
(If EAP has been implemented) |
| WHO |
| FLS Director |
| HOW |
| PA System located at the FCC. |
| WHY |
Provide occupants all available information including:
|
FLS Director immediately conducts a rapid assessment of existing conditions.
| ACTION |
| Notify the JSOC at 212-417-7116 & Property Management Office at 212-528-2179. |
| WHO |
| FLS Director
EAP Brigade |
| HOW |
| Hand held radio, cell phone, or telephone. |
| WHY |
| Provide information as described above. |
| ACTION |
| A Power Outage does not automatically require an Evacuation of the Building; implementation of the Emergency Action Plan should be considered.
Determine EAP Response. |
| WHO |
| FLS Director
EAP Brigade |
| HOW |
| EAP Brigade “Huddle” at FCC: Ascertain as much information as possible and assess available Response. |
| WHY |
| Provide protection and warning to the greatest number of Persons possible. |
FLS Director immediately conducts a rapid assessment of existing conditions.
| ACTION |
| Ensure Emergency Backup Generator has been activated and is functioning properly. |
| WHO |
| FLS Director
Building Engineers |
| HOW |
| Conduct onsite inspection of Systems. |
| WHY |
| Provides Backup Power to Building Life Safety Systems. |
| ACTION |
| Ensure Life-Safety Systems are operating.
Conduct a visual inspection at FCC and BMS. |
| WHO |
| FLS Director
Building Engineers |
| HOW |
| Conduct a visual inspection at FCC. |
| WHY |
| Failure of any Life-Safety Systems would require a possible Building Evacuation. |